emiT Timeline (* tasks that must be completed by the given date)


July 10th

All equipment required for detector tests arrives/exists at UW

* HV crate and cables <HPM> (Operational / lacks bells and whistles)

-Labview update (Completed)

* Proton paddle upgrades* <HPM> (Testing is in progress)

* LED pulsers <PP> (Testing in progress)

* Cooling <JSN,HPM> (Operational)

* Detectors <HPM,SJF> (All detectors are at UW)

Aug 20th Shutdown for cold source upgrade
Sept 30th Beamline modification plan <FEW,JSN>

-shortening of flight tubes

* HV Monitors <HPM,JSN>

Validation plan <HPM,JSN,HPM>

* All coils <KPC,TC>

* Beta repairs (bases <SJF> and replacement of tube <HPM>)

*
Beta power supply <SJF,JFW,AG>

*
DAQ <JFW,MH, HPM>

*
Electronics and trigger <JFW,HPM,BF>

Oct 15th Ship detector to NIST
Oct 15th-Jan 1st 02 Build up detector on beamline

Detector tests and field mapping (3 FTE + 3 needed)

* Translation stage for 10 gauss flux gate (automated ?) <KPC,TC>

* Beamtube with crosshairs (checkout) <KPC,TC>

Dec 1st

Estimates of min. required detector performance <KPC,AG>

* Decision required regarding additional Monte Carlo detail

Jan 1st-20th

Alignment and beam characterization (3 FTE + 4 needed)

Beam profile <MSD,JSN>

Polarization measurements

Jan 20th

Run Start (3 FTE + 1 needed)

ATP test

* Estimate of required run time.

Summer 2002

Polarization profile measurements

* 3He cell, coils allow transverse field <GJ>




As of Monday, September 10, 2001

Timeline for proton paddle upgrades ( HPM whip, * Task completed)

Sept 14th Additional full size Motherboard material arrives.
A few days later we will have a full size Motherboard setup for testing.
At this point we are seriously considering having the Motherboards made commercially.
Sept 17th Preamps ship
Sept 19th Repair and polishing of Quansit hut complete.
(This includes focusing tube assembly).
Sept 20th Cooling design complete.
Sept 25th Preamp stuffing complete.
Sept 30th Motherboards complete.
Cooling Modifications complete.